First floor planks have been installed
Week 12 of the Phase 3 programme.
The ground floor planks have been installed and the ground floor to first floor blockwork is progressing. First floor planks are programmed to be delivered/installed w/c 11th March 2013.
Construction of the main carpark is on-going and nearing completion.
The work is on programme despite the weather!