Development

Good progress being made on the rear of the building

The project is now in week 20 of the 34 week programme.

The roof structure is ongoing and the roof covering work will commence shortly.

Internally, screeding has been completed to the lower ground and ground floors. The first fix work is complete to the lower ground and ongoing to the ground floor.

Go Back